The '''Hollywood Boulevard pedestrian bridge''' was a proposed pedestrian and bicycle connection between the suburbs of [[Homewood]] and [[Mountain Brook]] across [[U.S. Highway 280]] near the existing [[Hollywood Boulevard]] vehicular overpass, built in the 1960s with two lanes of traffic and no pedestrian path.
The '''Hollywood Boulevard pedestrian bridge''' was a proposed pedestrian and bicycle connection between the suburbs of [[Homewood]] and [[Mountain Brook]] across [[U.S. Highway 280]] near the existing [[Hollywood Boulevard]] vehicular overpass, which was built in the 1960s with two lanes of traffic, 24" tall guardrails, and no pedestrian path.


The [[Homewood City Council]] first approved a resolution to pursue development of such a bridge on [[August 13]], following discussions with Mountain Brook and [[Birmingham]] coordinated by State Representative [[Paul DeMarco]] (R-[[Alabama House District 46|District 46]]) had already begun. Homewood City Council member [[Jackie Langlow]] was also a leader, and the project was overwhelmingly supported by the 900-member [[Birmingham Track Club]], headed by [[Jennifer Andress]].
The [[Homewood City Council]] first approved a resolution to pursue development of such a bridge on [[August 13]], following discussions with Mountain Brook and [[Birmingham]] coordinated by State Representative [[Paul DeMarco]] (R-[[Alabama House District 46|District 46]]) had already begun. Homewood City Council member [[Jackie Langlow]] was also a leader, and the project was overwhelmingly supported by the 900-member [[Birmingham Track Club]], headed by [[Jennifer Andress]] as a major improvement to safety for runners.


As discussions progressed, it became clear that initial budget estimates were insufficient. Homewood Council member [[Jesse Vogtle]] also noted that with the intersection improvements made to the highway by the [[Alabama Department of Transportation]], more drivers were using the Hollywood Boulevard overpass as a "Michigan left" alternative. The cities became concerned that if they did erect a parallel pedestrian bridge, that it might have to be demolished soon later if ALDOT moved to replace the overpass.
DeMarco lost his seat in the [[2014 primary elections|2014 Republican primary]], and Andress was elected to the Homewood City Council in [[2016 Jefferson County municipal elections#Homewood|2016]], with the bridge project as a key part of her campaign. She took up the mantle of leading the project as planning continued. In November [[2016]] both Homewood and Mountain Brook approved $6,000 each as a 20% match for a feasibility study through the [[Metropolitan Planning Organization]] and [[Regional Planning Commission of Greater Birmingham]]'s APPLE (Advanced Planning, Programming and Logical Engineering) program.


Meanwhile, DeMarco lost his seat in the [[2014 primary elections|2014 Republican primary]], and Andress was elected to the Homewood City Council in [[2016 Jefferson County municipal elections#Homewood|2016]]. She took up the mantle of leading the project as planning continued. In November [[2016]] both Homewood and Mountain Brook approved $6,000 each as a 20% match for a feasibility study through the [[Metropolitan Planning Organization]] and [[Regional Planning Commission of Greater Birmingham]]'s APPLE (Advanced Planning, Programming and Logical Engineering) program. That study, which compared various design options and funding schemes over the longer section of the boulevard from [[Malaga Avenue]] to [[Mountain Brook Village]], was completed by [[Sain Associates]] in June [[2018]].
That study, which compared various design options and funding schemes over the longer section of the boulevard from [[Malaga Avenue]] to [[Mountain Brook Village]]. RPCGB planners [[Mike Kaczorowski]] and [[Jennifer Brown]] presented preliminary findings along with various design options to a group meeting of officials from Homewood, Mountain Brook and Birmingham in January [[2018]]. Also attending were DeMarco and his successor as District 46 Representative [[David Faulkner]]. The planners looked at two alternatives for providing a protected pedestrian path on an expanded overpass and two alternatives for building a separate pedestrian bridge. They also evaluated the option of merely restriping the overpass to provide a slightly wider shoulder and using the planned [[Zoo Connector Trail]] as the preferred path for pedestrian connection between Homewood and Mountain Brook. After the meeting it was noted that stakeholders preferred a separate 10-foot wide pedestrian bridge north of the overpass, which it was hoped would be feasible without federal funding.


<!--In [[2018]] RPCGB planners [[Mike Kaczorowski]] and [[Jennifer Brown]] presented three options to a group meeting of officials from Homewood, Mountain Brook and Birmingham. Also attending were DeMarco and his successor as District 46 Representative [[David Faulkner]]. The three options included:
[[Sain Associates]] completed their feasibility study in June [[2018]]. They estimated that the preferred option for a separate bridge would cost approximately $1,165,000. It would be about 130 feet long and would extend from [[Union Hill Road]] at the corner of [[Union Hill Cemetery]] to the parking lot of [[The Hollywood]] shopping center. Placement of the pre-fabricated bridge structure was expected to require the highway to be closed for two days.


# Option 1: A separate pedestrian bridge on the north side of the existing bridge, with sidewalks along the north side of Hollywood Boulevard. A traffic signal and crosswalk would also be added on the east side of the bridge, at the off-ramp from U.S. 280. This option costs around $1.4 million.
The '''Highway 280 Neighborhood Improvement District Cooperative'''<!--also called the "Highway 280 Public Road Cooperative District"--> was established in August 2018 to coordinate project funding on behalf of the cities involved. [[Jefferson County Commission]]er [[Steve Ammons]] served as president of that group, with Andress as vice-president and [[Mountain Brook City Council]]or [[Alice Womack]] as treasurer. Other members included [[Virginia Smith]] and [[Peter Wright]], presidents of the Mountain Brook and Homewood City Councils respectively, and [[Darrell O'Quinn]] and [[Valerie Abbott]] of the [[Birmingham City Council]].
# Option 2: Widen the existing bridge to add a pedestrian lane on the north side, as well as a left turn lane for the U.S. 280 on-ramp. This option would also include the sidewalks, crosswalk and traffic signal from Option 1, and would cost around $3.87 million.
# Option 3: This is nearly identical to Option 2, but with the pedestrian lane and sidewalks on the south side of Hollywood Boulevard. Brown said this option is slightly cheaper for the city, at $3.7 million, and would be less likely to impact Union Hill Cemetery, but it would be more likely to impact homeowners' yards and driveways with sidewalk construction.


8 foot-wide, 130 foot-long steel-framed pedestrian bridge which would span [[U.S. Highway 280]] alongside [[Hollywood Boulevard]] from [[Union Hill Road]] to [[The Hollywood]] shopping center. The bridge would create a safer connection-->
Homewood and Mountain Brook each pledged $200,000. [[Alabama State Senate|Alabama State Senator]] [[Slade Blackwell]] (R-[[Alabama Senate District 15|District 15]]) allocated $150,000 from the [[Jefferson County Community Service Fund]] toward the project. Other members of the [[Jefferson County Legislative Delegation]] also awarded grants from the same fund, totaling $262,500. The Birmingham Track Club and [[Trak Shak]] held a fundraising event and made a sizeable contribution. Other donations were received from individuals and businesses, and from the Hollywood Garden Club. The amount pledged surpassed $1.1 million in October 2018. Andress expected that construction could begin in spring [[2019]].


The proposal has been shepherded by [[Homewood City Council]] member [[Jennifer Andress]]. The two cities each pledged $200,000 in funding, alongside a commitment of $150,000 from [[Alabama State Senate|Alabama State Senator]] [[Slade Blackwell]]'s discretionary funds for capital projects. Additional funds were to be secured from private donors and from the [[State of Alabama]]. Private contributions have been secured from the [[Hollywood Garden Club]], the [[Birmingham Track Club]] and [[Trak Shak]].
Before any contracts were signed, however, the [[Jefferson County Roads and Transportation Department]] and the [[Alabama Department of Transportation]] (ALDOT) determined that they preferred to replace the entire overpass to better accommodate both vehicular and pedestrian use, and would cost around $3 million. The idea of a separate pedestrian bridge was set aside and progress on the project was stalled in [[2020]] by the [[COVID-19 pandemic]].


That initial scheme was budgeted at $1.17 million. Placement of the pre-fabricated bridge structure was expected to require the highway to be closed for two days. Andress expected to secure all necessary funding by October [[2018]], with construction anticipated in Spring [[2019]].  
In January [[2021]] the Highway 280 Neighborhood Improvement District Cooperative met with the County Transportation Department to request that the project move forward. Andress and Ammons announced in September [[2021]] that preliminary design of the improved overpass had been completed, and was pending approvals from ALDOT. The new bridge would add a left turn lane for cars entering U.S. Highway 280 eastbound and a traffic signal at the top of the exit ramp from 280 westbound. The protected pedestrian path would occupy the northern edge of the bridge. The Cooperative then contracted with AECOM of Los Angeles, California to produce engineering drawings for bidding, which was expected to take place in August [[2022]].


Before any contracts were signed, the [[Jefferson County Roads and Transportation Department]] and the [[Alabama Department of Transportation]] developed plans to widen the existing vehicular bridge and add a traffic signal for cars exiting onto Hollywood Boulevard from Highway 280. Progress on the project was delayed due to the [[COVID-19 pandemic]].
Meanwhile, ALDOT began planning to widen U.S. Highway 280 to four lanes in each direction between Hollywood Boulevard and [[I-459]]. Progress on the overpass replacement was delayed again to accommodate the highway project.
 
The changes and delays led Birmingham, Homewood and Mountain Brook to revise their budget for the pedestrian bridge itself to $2 million and to commission AECOM of Los Angeles, California to produce contract documents for bids to be solicited in August [[2022]].


==References==
==References==
Line 28: Line 24:
* Cromwell, Sydney (November 21, 2016) "[https://thehomewoodstar.com/news/hollywood-pedestrian-bridge-moving-forward-again1121/ Hollywood pedestrian bridge moving forward again]." {{HS}}
* Cromwell, Sydney (November 21, 2016) "[https://thehomewoodstar.com/news/hollywood-pedestrian-bridge-moving-forward-again1121/ Hollywood pedestrian bridge moving forward again]." {{HS}}
* Cromwell, Sydney (November 28, 2016) "[https://thehomewoodstar.com/news/council-approves-study-for-hollywood-pedestrian-bridge1128/ Council approves study for Hollywood pedestrian bridge]." {{HS}}
* Cromwell, Sydney (November 28, 2016) "[https://thehomewoodstar.com/news/council-approves-study-for-hollywood-pedestrian-bridge1128/ Council approves study for Hollywood pedestrian bridge]." {{HS}}
* Cromwell, Sydney (June 11, 2018) "[https://thehomewoodstar.com/news/hollywood-pedestrian-bridge-could-be-funded-this-fall611/ Hollywood pedestrian bridge could be funded this fall]." {{HS}}
* Edgemon, Erin (August 16, 2018) "Pedestrian bridge over U.S. 280 planned for Homewood, Mountain Brook." {{BN}}
* Edgemon, Erin (August 16, 2018) "Pedestrian bridge over U.S. 280 planned for Homewood, Mountain Brook." {{BN}}
* Coker, Angel (August 21, 2018) "Pedestrian bridge to connect Homewood, Mountain Brook moves forward." {{BBJ}}
* Coker, Angel (August 21, 2018) "Pedestrian bridge to connect Homewood, Mountain Brook moves forward." {{BBJ}}
* Andress, Jennifer (October 31, 2018) "[https://thehomewoodstar.com/peopleplaces/legislators-donate-to-pedestrian-bridge-project1030/ Legislators donate to pedestrian bridge project]" {{HS}}
* Coker, Angel (April 11, 2019) "Homewood pedestrian bridge moves forward." {{BBJ}}
* Coker, Angel (April 11, 2019) "Homewood pedestrian bridge moves forward." {{BBJ}}
* Mann, Joshua (September 21, 2021) "Hollywood bridge project expands, begins to move again." {{BBJ}}
* Mann, Joshua (September 21, 2021) "Hollywood bridge project expands, begins to move again." {{BBJ}}
* Croxson, Madison (September 21, 2021) "[https://bhamnow.com/2021/09/21/highway-280-is-getting-a-new-bridgedetails-here/ Highway 280 is getting a new bridge—details here]" {{BNow}}
* Embry, Neal (September 22, 2021) "[https://thehomewoodstar.com/news/pedestrian-bridge-thoroughfare-improvement-project-enters-fi/ Pedestrian bridge, thoroughfare improvement project enters final design phase]." {{HS}}
* Chambers, Jesse (October 23, 2021) "[https://www.villagelivingonline.com/news/officials-move-forward-with-plans-to-improve-bridge-at-us-28/ Officials move forward with plans to improve bridge at US 280, Hollywood Boulevard]." ''[[Village Living]]''


[[Category:2022 buildings]]
[[Category:Proposed developments]]
[[Category:Pedestrian bridges]]
[[Category:Hollywood Boulevard]]
[[Category:Hollywood Boulevard]]
[[Category:U.S. Highway 280]]

Revision as of 14:40, 28 September 2023

The Hollywood Boulevard pedestrian bridge was a proposed pedestrian and bicycle connection between the suburbs of Homewood and Mountain Brook across U.S. Highway 280 near the existing Hollywood Boulevard vehicular overpass, which was built in the 1960s with two lanes of traffic, 24" tall guardrails, and no pedestrian path.

The Homewood City Council first approved a resolution to pursue development of such a bridge on August 13, following discussions with Mountain Brook and Birmingham coordinated by State Representative Paul DeMarco (R-District 46) had already begun. Homewood City Council member Jackie Langlow was also a leader, and the project was overwhelmingly supported by the 900-member Birmingham Track Club, headed by Jennifer Andress as a major improvement to safety for runners.

DeMarco lost his seat in the 2014 Republican primary, and Andress was elected to the Homewood City Council in 2016, with the bridge project as a key part of her campaign. She took up the mantle of leading the project as planning continued. In November 2016 both Homewood and Mountain Brook approved $6,000 each as a 20% match for a feasibility study through the Metropolitan Planning Organization and Regional Planning Commission of Greater Birmingham's APPLE (Advanced Planning, Programming and Logical Engineering) program.

That study, which compared various design options and funding schemes over the longer section of the boulevard from Malaga Avenue to Mountain Brook Village. RPCGB planners Mike Kaczorowski and Jennifer Brown presented preliminary findings along with various design options to a group meeting of officials from Homewood, Mountain Brook and Birmingham in January 2018. Also attending were DeMarco and his successor as District 46 Representative David Faulkner. The planners looked at two alternatives for providing a protected pedestrian path on an expanded overpass and two alternatives for building a separate pedestrian bridge. They also evaluated the option of merely restriping the overpass to provide a slightly wider shoulder and using the planned Zoo Connector Trail as the preferred path for pedestrian connection between Homewood and Mountain Brook. After the meeting it was noted that stakeholders preferred a separate 10-foot wide pedestrian bridge north of the overpass, which it was hoped would be feasible without federal funding.

Sain Associates completed their feasibility study in June 2018. They estimated that the preferred option for a separate bridge would cost approximately $1,165,000. It would be about 130 feet long and would extend from Union Hill Road at the corner of Union Hill Cemetery to the parking lot of The Hollywood shopping center. Placement of the pre-fabricated bridge structure was expected to require the highway to be closed for two days.

The Highway 280 Neighborhood Improvement District Cooperative was established in August 2018 to coordinate project funding on behalf of the cities involved. Jefferson County Commissioner Steve Ammons served as president of that group, with Andress as vice-president and Mountain Brook City Councilor Alice Womack as treasurer. Other members included Virginia Smith and Peter Wright, presidents of the Mountain Brook and Homewood City Councils respectively, and Darrell O'Quinn and Valerie Abbott of the Birmingham City Council.

Homewood and Mountain Brook each pledged $200,000. Alabama State Senator Slade Blackwell (R-District 15) allocated $150,000 from the Jefferson County Community Service Fund toward the project. Other members of the Jefferson County Legislative Delegation also awarded grants from the same fund, totaling $262,500. The Birmingham Track Club and Trak Shak held a fundraising event and made a sizeable contribution. Other donations were received from individuals and businesses, and from the Hollywood Garden Club. The amount pledged surpassed $1.1 million in October 2018. Andress expected that construction could begin in spring 2019.

Before any contracts were signed, however, the Jefferson County Roads and Transportation Department and the Alabama Department of Transportation (ALDOT) determined that they preferred to replace the entire overpass to better accommodate both vehicular and pedestrian use, and would cost around $3 million. The idea of a separate pedestrian bridge was set aside and progress on the project was stalled in 2020 by the COVID-19 pandemic.

In January 2021 the Highway 280 Neighborhood Improvement District Cooperative met with the County Transportation Department to request that the project move forward. Andress and Ammons announced in September 2021 that preliminary design of the improved overpass had been completed, and was pending approvals from ALDOT. The new bridge would add a left turn lane for cars entering U.S. Highway 280 eastbound and a traffic signal at the top of the exit ramp from 280 westbound. The protected pedestrian path would occupy the northern edge of the bridge. The Cooperative then contracted with AECOM of Los Angeles, California to produce engineering drawings for bidding, which was expected to take place in August 2022.

Meanwhile, ALDOT began planning to widen U.S. Highway 280 to four lanes in each direction between Hollywood Boulevard and I-459. Progress on the overpass replacement was delayed again to accommodate the highway project.